Institutional-Repository, University of Moratuwa.  

Rellability improvement in the 33kV distribution feeder using optimum positioning of auto reclosers

Show simple item record

dc.contributor.advisor Rodrigo, WDAS
dc.contributor.author De Silva, PHNS
dc.date.accessioned 2015-10-29T15:35:04Z
dc.date.available 2015-10-29T15:35:04Z
dc.date.issued 2015-10-29
dc.identifier.uri http://dl.lib.mrt.ac.lk/handle/123/11502
dc.description.abstract In an era where Sri Lanka economy is going towards a drastically higher growth it is highly important to have a reliable electricity network in the country. To improve the reliability of the distribution network, Distribution Licensees improve the system capacity and at the same time install protective devices to reduce the interrupted area due to an electrical fault in the network. For this Auto Reclosers and Fuses are used in the Distribution Network. In developed countries the installation of Protective devices are done optimally and techniques have been developed. In Sri Lanka, the process of planning, design and construction of transmission and medium voltage power lines is solely authoritative by Transmission Licensee and Five Distribution Licensees of the country. At present there is no proper way of selecting optimal location for the installation of Auto reclosers is practiced in either of these Licensees. As the first step of this study, a research survey was done about the optimal location selection methods researched in other countries. A suitable objective function was modeled to find the optimal location to install an Auto Recloser with the constraint of finding two optimal locations in series. This report will discuss the objective function formation to find the optimal location for the Auto Recloser and also as a supporting study a pilot project done on how to coordinate the fuses with the Auto Reclosers and the Circuit Breakers at the Grid Substation is also included. Major Findings of this research: Optimal locations to install an Auto recloser for a feeder according to the SAIDI values of substations and the energy consumptions of bulk and retail consumers connected to that specific feeder. Findings of the pilot project: how to co-ordinate the fuses installed on a feeder and how to decide the rating of a fuse to be installed on the feeder by maintaining the protection co-ordination with other protective devices on the feeder en_US
dc.language.iso en en_US
dc.subject MSc in Electrical Engineering
dc.subject ELECTRICAL ENGINEERING-Dissertations
dc.subject ELECTRICITY NETWORK-Reliability
dc.subject Distribution licensees
dc.title Rellability improvement in the 33kV distribution feeder using optimum positioning of auto reclosers en_US
dc.type Thesis-Full-text en_US
dc.identifier.faculty Engineering en_US
dc.identifier.degree Master of Science in Electrical Engineering en_US
dc.identifier.department Department of Electrical Engineering en_US
dc.date.accept 2015-05
dc.identifier.accno 109317 en_US


Files in this item

This item appears in the following Collection(s)

Show simple item record