Abstract:
Delays are common in all type of construction projects and therefore delays are very
significant for all types of construction projects. Mainly the fault or mistake is by client,
architect,contractor and other stakeholders.
The delay is considered as a widespread crisis in construction projects. The delay occurs as a
result of an act or failure to act by contracting parties as well as by outside forces. Sri Lankan
construction industry faces a significant rate of delays in project delivery. The causes of
delays in construction in Sri Lankan have been identified and have been addressed
individually by stakeholders. However, the delay occurs in almost all projects in Sri Lanka
continuously.The purpose of this research was to identify the most significant causes of
delays in construction in Sri Lanka.
Following an in-depth review of literature's in various parts of the world, 44 causes of was
first formulated. These identified causes were presented, based on Delphi technique, to a
panel of experts from construction industry consisting of Senior Quantity Surveyors, Senior
Project Managers, Senior Architects and Senior Engineers who are playing a managerial role.
The experts were requested to express their opinion on the level of significance on each cause
and the results were statistically summarized.
It was observed that there are eight most significant causes of delays exist in Sri Lankan
construction projects viz.; poor planning and scheduling, delay in obtaining permits and
permissions,poor site management, design deficiencies, suspension of works by owner,
contractor's financial difficulties, variations and slow decision making by owner. Out of these
ten causes,poor planning and scheduling has recorded extremely significant and all other
seven causes have recorded as very significant. The findings were slightly different to those
of previous studies in other countries.