L STUDY OF OPTIMAL LOCATION FOR CAPACITOR INSTALLATION IN A 220/13^33 kV GRID SUBSTATION A dissertation submitted to the Department of Electrical Engineering University of Moratuwa in partial fulfillment of the requirements for the Degree of Master of Science LIBRARY UNIVERSITY OF MORATUWA, SRI LANKA MORATUWA by W.M.S. DEEPIKA WIJESINGHE Supervised by: Dr. } P Karunadasa University of Moratuwa 92425 Department of Electrical Engineering University of Moratuwa, Sri Lanka ,3 foj- 3- C ^ 4 3 j February, 2009 T H 92425 LIBRARY 5 Deceleration The work submitted in this dissertation is the result of my own investigation, except where otherwise stated. It has not already been accepted for any degree, and is also not being concurrently submitted for any other degree. Name of the candidate: W.M.S. Deepika Wijesinghe Date: February 12, 2009 I endorse the declaration by the candidate. 'cy oevp' Name of the Supervisor: Dr. J P Karunadasa Date: 1 Table of Content Item Page Table of Content » Abstract i v Acknowledgement v ' List of Figures V11 List of Tables List of Tables ' x 1. Introduction 1 1.1 Background of the research 1 1.2 Motivation of this study 3 1.3 Objectives 4 2. Literature Review 5 2.1 Applicable Standards 5 2.2 The Capacitor Unit 6 2.3 Fuse technologies 6 2.4 Capacitor Bank Design 10 2.5 Grounded Wye-Connected Banks 10 2.6 Multiple Units in Series Phase to Ground - Double Wye 11 2.7 Ungrounded Wye-Connected Banks 12 2.8 Multiple Units in Series Phase to Neutral - Single Wye 12 2.9 Delta-connected Banks '. 13 2.10 H Configuration 13 3. Methodology 1 4 3.1 Introduction 14 3.2 Software for transient analysis 14 3.3 Development of the Software Model 15 3.4 Different fault conditions used for Analysis 23 4. Results and Analysis 24 4.1 Normal Switching of Capacitor 24 4.2 Fast Switching of capacitor Banks 32 4.3 Switching of 33 kV load to the system 34 4.4 Disconnection of loaded distribution feeder from the system 35 4.5 Capacitor Unit Failure 36 4.6 Unbalance feeder faults in the system - X - - 38 ;; ii V , c w . . . . ' 4.8 Three phase to ground fault at 132 kV feeder 40 4.9 Lightning to 220 kV Feeder 42 5. Conclusion 5.1 Switching of Capacitor Banks 43 5.2 Switching of distribution loads 44 5.3 Capacitor unit failure 44 5.4 Unbalance system faults 44 5.5 Balance system Faults 44 5.6 Lightning to 220 kV Feeder 44 5.7 Summary 45 5.8 Recommendation 45 Annexure 1 - Proposed options for Pannipitiya GSS 48 Annexure 2 - The model Developed for simulation 49 Annexure 3 - 83.3 MVA Transformer data sheets 50 Annexure 4 - 31.5 MVA Transformer data sheets 51 Annexure 5 - 200kVA Transformer data sheet 52 Annexure 6 - Capacitor bank data sheets 53 Annexure 7 - Transmission line data sheets 54 iii Abstract In the island wide transmission network of Ceylon Electricity Board, there are 33kV Breaker Switch Capacitor Banks at twelve locations for improving the efficiency and quality of power. The capacitor bank installed at Pannipitiya Grid Substation, which is the highest capacity installed in a grid substation of the CEB network was failed immediately after connecting to the system. Several studies were conducted to identify reasons of the failure. However the final recommendation is still pending. Placement of capacitor banks in a grid substation is a major factor, influencing the reliability and efficient operation of capacitor banks. Therefore, this study was focused on to determine the preferred location of installing capacitor banks in a 220/132/33 kV grid substation. The two of possible locations are at 33kV tertiary of the power transformers and at the 33 kV load bus. Influences on capacitor banks under different fault conditions were analyzed in this study, while simulating the grid model built using Simulink in MATLAB program. Positive and negative impacts were found in respect of the two identified locations. • Switching stresses on capacitors of the bank is less when capacitors are installed at tertiary of the power transformers compared to the case when capacitors are at the 33 kV load busbar. • For balance or unbalanced feeder faults, preferred location is the 33 kV load busbar, since voltage and current fluctuations are less compared to the other location. iv • In case of lightning strikes at high voltage side, capacitors have less stresses when located at 33 kV load busbar. As such, it is recommended to connect capacitor banks at tertiary of 220/132/33 kV transformers of grid substations in industrial areas such as Export processing Zones, because the capacitor banks are subjected to frequent switching due to high load variations of the industrial load. Installation of capacitor banks at 33 kV load busbars is recommended to the grid substations where there are long power transmission lines with frequent feeder faults because such feeder faults have less influence on capacitor banks when they are located at the 33 kV load busbars. v Acknowledgement I sincerely thank my supervisor, Dr. J.P Karunadasa for his excellent corporation and guidance offered for the successful completion of this study. I extend my sincere thanks to lecturers of postgraduate study course in Electrical Engineering, University of Moratuwa, Sri Lanka, who gave me the theoretical knowledge and encouragement in bringing up this academic work. I specially thank Mrs. Y. M. Samarasinghe, Deputy General Manager (Western Province South), who initially put forth the idea of studying the ideal location for installation of capacitor banks in grid substations. I highly appreciate my friends and colleagues, specially Mr. Kurrupu Dharmasiri for their help offered to collect data and information required to prepare a realistic model for the study. Finally, I thank many individuals for making this research a success, who have not been mentioned here personally. vt List of Figures Figure 2 - Cross section of a Power Capacitor Unit 6 Figure 3 - Capacitor Fuse Technologies 7 Figure 4 - Externally fused type 7 Figure 5 - Internally fused shunt capacitor bank and capacitor unit 8 Figure 6 - Fuseless shunt capacitor bank and series string 9 Figure 7 - Multiple units grounded single Wye 10 Figure 8 - Multiple units grounded double Wye 11 Figure 9 - Multiple units ungrounded single Wye 12 Figure 10 - Multiple units ungrounded double Wye 12 Figure 10 - Two options considered for the Study 15 Figure 12 - Wiring Diagram of Capacitor Banks 19 Figure 13- capacitor model used to study the unit failure effect 19 Figure 14 - Lightning Impulse Model 20 Figure 15 - Lightning Impulse at 220 kV busbar 21 Figure 17- Equivalent model during instant of switching 24 Figure 18 - Current transient during switching of 1st 5Mvar capacitor bank 25 Figure 19 - Voltage transient during switching of 1st 5Mvar capacitor bank 25 Figure 20 - Current transient during switching of 2nd 5 Mvar capacitor bank 26 Figure 21 - Voltage transient during switching of 2nd 5Mvar capacitor bank 27 Figure 22 - Current transient during switching of 3rd 20Mvar capacitor bank 27 Figure 23 - Voltage transient during witching of 3rd 20Mvar capacitor bank 28 Figure 24 - Inrush current at the switching of 3rd step 20 Mvar capacitances 29 Figure 25 - Current transient during switching of 4th 20Mvar capacitor bank 30 Figure 26 - Voltage transient during switching of 4th 20Mvar capacitor bank 31 Figure 27 - Voltage transient during fast switchng of capaciotor banks 31 Figure 28 - Current transient during fast switchng of capaciotor banks 32 Figure 29 - Voltage transient during switched the loaded 33 kV feeder 33 Figure 30 - Current transient during switched the loaded 33kV feeder 33 Figure 31 - Voltage transient during disconnection of loaded 33kV feeder 34 Figure 32 - Current transient during disconnection of loaded 33kV feeder 34 Figure 33 - Voltage transient during capacitor unit failure with grounded case 35 Figure 34 - Current transient during capacitor unit failure in grounded case 35 Figure 35 - Voltage transient during capacitor unit failure with ungrounded case 36 vii Figure 36 - Current transient during capacitor unit failure with ungrounded case 37 Figure 37 - Voltage transient during 33 kV line fault at transformer option 38 Figure 38 - Voltage transient during 33 kV line fault at busbar option 38 Figure 39 - Current transient during 33 kV line fault at transformer option 39 Figure 40 - Current transient during 33 kV line fault at busbarr option 39 Figure 41 - Voltage transient during three phase to ground fault at 33 kV feeder 40 Figure 42 - Current transient during three phase to ground fault at 33 kV feeder 40 Figure 43 - Voltage transient during three phase to ground fault at 132 kV feeder 41 Figure 44 - Current transient during three phase to ground fault at 132 kV feeder 41 Figure 45 - Voltage transient at capacitor during lightning stroke at 220 kV feeder 42 Figure 46 - Transient current at capacitor during lightning stroke at 220 kV feeder 42 viu List of Tables Table 1 - Power capacitors installed locations in CEB network 3 Table 2 - 83.33MVA Transformer Data 17 Table 3 -31 .5 MVA Transformer Data 17 Table 4 - 200 kVA Earthing Transformer Data 17 Table 4 - Transmission and Distribution Line Data 18 Table 5- Calculated values for the switching of 5 Mvar capacitor bank 24 Table 6 - Calculated values for the switching of second 5 Mvar capacitor bank 26 Table 7- Steady state currents during switching of 41'1 stage 29 ix