POST TECHNICAL AND ECONOMICAL ANALYSIS OF A 132 KV TRANSMISSION SUB NETWORK OF CEYLON ELECTRICITY BOARD A dissertation submitted to the Department of Electrical Engineering, University of Moratuwa In partial fulfillment of the requirements for the Degree of Master of Engineering. By Jayasekera Mudalige Kanishka Jayasekera Supervised by: Professor J.R. Lucas Department of Electrical Engineering University of Moratuwa, Sri Lanka. 2006 86326 Abstract Power transmission network components are planned and designed for 30 to 40 years operating period in the network after construction. From planning stage to construction stage it takes about four years. The horizon of the planning process of Ceylon Electricity Board is ten years and each year the planning process is reviewed. Therefore ideally once a transmission line is constructed and energized, it should serve the system requirements for 30 to 40 years. In a transmission network, grid substations and power stations are connected to each other. More number of grid substations are appeared in areas where industrially and commercially populated. The generated bulk power from major power stations are transferred to the heavily populated areas through grid substations. As the number of grid substations are increased in an area, power stations may also be added to the system with in the same area, to cater the demanded load maintaining the quality of supply. The cost of the transmission line construction is large and it varies according to the lengths of the line and the capacity. The optimal outcome of the combination of planning and designing of a transmission line is, at the energization, the line should be loaded minimum, the construction cost should be minimum and it should serve the system for full designed period maintaining the system security. An evaluation was done for the 132 kV transmission network connecting Kolonnawa GS, Kelaniya GS, Kotugoda GS, Sapugaskanda GS, Biyagama GS and Asia Power PS which was reconstructed recently. The evaluation was based on load flow studies and the cost of construction. The load flow studies were done using the software of Power System Simulator for Engineering. It is observed that mere reconstruction or upgrading the old system will not give the optimal solution in network expansion. With the addition of more and more grid substations to the system, re-arrangement of possible transmission network sections would result better and optimal network behaviour. DECLARATION The work submitted in this disse11ation is the result of my own investigation, except where otherwise stated. It has not already been accepted for any degree, and is also not being concurrently submitted for any other degree. ~era 12.01.2006 j I endorse the declaration by the candidate. ~ Professor J.R. Lucas. ..~ ' ,.- ~ :,.~ .. v Declaration Abstract Acknowledgement List of Figures List ofTables List of principal symbols 1. Introduction 1.1 Background 1.2 Motivation 1.2 Scope 2. Statement of the problem 2.1 Preliminaries 2.2 Problem identification 2.2.1 A load flow analysis CONTENTS 2.2.2 Present sub network operating system 2.2.3 Recorded recent loads of sub network 2.3 Analysis for a optimal network arrangement 3. Analysis 3. 1 Possible network configurations j 3.1.1 Alternative 01- Old sub network in the transmission system 2005 3.1.2 Alternative 02- Adding new line in between Sapugaskanda and Biyagama 3.1.3 Alternative 03- Old lines in between Kolonnawa and Kotugoda 3.1.4 Alternative 04- Old line in between Kolonnawa and Kelaniya 3.1.5 Alternative 05- Old line in between Kelaniya and Kotugoda 3.1.6 Alternative 06- No line in between Kolonnawa and Kelaniya 3.1.7 Alternative 07- No line in between Kelaniya and Kotugoda 3.1.8 Alternative 08- No lines in bet\\'een Kolonnawa and Kotugoda 3.1.9 Alternative 09- Asia Power PS connecting to Sapugaskanda 3.1.10 Alternative 10- Combination of Alternative 08 and Alternative 09 3.2 Transmission line data and capacities of grid sQ~tation 3.3 Tools of analysis 3.4 Day peak and night loads 3.5 Peak load analysis 3.5. 1 Alternative 0 1- Old sub network in the transmission system 2{)05 3.5.2 Al ternative 02- Adding new line in between Sapugaskanda and I1iyagama 3.5.3 Alternative 03- Old lines in between Kolonnawa and Kotugoda 3.5.4 Alternative 04- Old line in between Kolonnawa and Kel~ni)4i'> 3.5.5 Alternative 05- Old line in between Kelaniya and Kotug6da 3.5.6 Alternative 06- No line in bct,,een Kolonnawa and Kc'lani) a / 3.5.7 Alternative 07- No line in between Kelaniya and Kotugoda 3.5.8 Alternative 08- No lines in between Kolonnawa and Kotugoda 3.5.9 Alternati\ c 09- Asia Power PS connecting to Sapugaskanda II I \ \ \ '1 \II \ Ill ') 2 6 6 6 6 7 10 13 14 14 14 14 14 15 15 15 16 16 16 16 17 18 18 21 21 24 27 27 30 ..,.., ~.) 37 39 ,.., -, "" 3.5.1 0 Alternative I 0- Combination of Alternative 08 and Alternative 09 3.6 Outcome of the analysis 3 .6.1 Alternative 11- No line in between Sapugaskanda and Biyagama 3.6.2 Alternative 12- Combination of Alternative 07 and Alternative 11 3.6.3 Summary of the outcome 3.7 Economical aspects 3. 7.1 Construction costs 3.7.1.1 Construction cost of the implemented system 3.7.1.2 Construction cost of Alternative 06 3. 7 .1.3 Construction cost of Alternative 08 3.7.1.4 Construction cost of Alternative 10 3.7.1.5 Construction cost of Alternative 11 3.7.1.6 CLmstruction cost of Alternati\'e 12 3.7.2 Summar: of construction cost 3.7.3 Cost of energy loss 4. Results 5. Conclusion References Appendix A- Forecasted loads for year 2005. Appendix B -Construction cost over loss of energy Ill .. ~ " j ..... ~ :... .. v 46 49 50 53 56 57 57 58 58 58 59 59 59 59 59 61 62 64 65 66 ACKNOWLEDGEMENT 1 express my gratitude to Professor J.R. Lucas and Professor H.Y.R. Perera in the Department of Electrical Engineering, University of Moratuwa, Sri Lanka., for their guidance and encouragement. My thanks are due to the staff of Department of Electrical Engineering, University of Moratuwa., for their assistance to me during my post graduate studies in the University. I am also grateful to the chief engineer and other engineers of the Transmission Planning office and system control centre of Ce) Ion f-lectricity Board for providing me the data. information and allo\\'ing me to use the computer facilities with relevant soft\\'arc. Finally. I should thank my family for helping me in various ways in making 111) post graduate studies a success. j .. ;,. " ;' ~ :.~- "' \ List of Figures Figure I. I .I Figure 1.1.2 Figure 1.1.3 Figure 2.2.1.1 Figure 2.2.1.2 Figure 2.2.2.1 Figure 2.2.2.2 Figure 3.5.1.1 Figure 3.5.1.2 Figure 3.5.1.3 Figure 3.5.1.4 Figure 3.5.2 Figure 3.5.3 Figure 3.5.4 Figure 3 .5.5 .I Figure 3.5.5.2 Figure 3.5.6.1 Figure 3.5.6.2 Figure 3.5.7.1 Figure 3.5.7.2 Figure 3.5.8.1 Figure 3.5.8.2 1-igure 3.5.9.1 Figure 3.5.9.2 Figure 3.5.1 0.1 Figure 3.5.10.2 Figure 3.6.1.1 Figure 3 .6. I .2 Figure 3.6.2.1 Figure 3.6.2.2 Location of the 132 kV transmission sub network in map of Sri Lanka 3 Configuration of sub nct\\'ork before construction 4 Configuration of sub network after construction 5 Load flow diagramme of the ex.isting system in night peak. , 8 Load flow diagramme of the existing system in day peak. 9 Load flo" diagramme for the present operating pattern in night peak. II Load flow diagrammc for the present operating pattern in day peak. 12 Load flO\\ diagramme for Alternative OJ in night peak. 22 Load flo" diagramme for Alternative 0 I in night peak when" Asia 23 Po\\er .. fails Load flo" diagram me for A lternati\e 0 I in night peak with Kclaniya 25 GS Load flo,, diagram me for Alternative 0 I in day peak with Kelaniya GS 26 Load flO\\ diagrammc for Alternative 02in nigl!¥peak. 28 Load flow diagrammc fo1 Alternative 03in night peak. 29 Load flow diagramme for Alternative 04in night peak. 31 Load flow diagrammc for Alternative 05in night peak. 32 Load flow diagramme for Alternative 05in day peak. 34 Load flow diagramme for Alternative 06in night peak. 35 Load flow diagramme for Alternative 06in day peak. 36 Load flow diagramme for Alternative 07in night peak. 38 Load flow diagramme for Alternative 07in day peak. 40 Load flow diagrammc for Alternative 08in night peak. 41 Load flow diagrammc fo1 Alternative 08in day peak. 42 Load flow diagramme for Alternati'e 09in night peak. 44 Load flow diagrammc for Alternative 09in day peak. 45 Load flow diagram me for Alternative I 0 in night peak. 4 7 Load flo" diagramme for Alternative 10 in day peak. 48 Load flo\\ diagramme for Alternative II in night peak. 5 I Load flo\\ diagramme for Alternative II in day peak. 52 Load flu,, diagramme for Alternati\e 12 in night peak. 5•1 Load flow diagramme for Altcrnati\e 12 in day peak. 55 A~ "' \'I -;. .... .; .;" ~ .; ,, List of Tables Table 2.2.1.1 Table 2.2.1.2 Table 2.2.2.1 Table 2.2.2.2 Table 2.2.3 Table 3.1.1 Table 3.1.2 Table 3.1.3 Table 3.1.4 Table 3.1.5 Table 3 1.6 Table 3. 1.7 Table 3.1.8 Table 3.1.9 Table 3. 1.1 0 Tabk 3.2 Table3.4 I Table 3 4.2 Table 3.4.3 Table 3.4.4 table 3.4.5 "I able 3.4.6 Table 3.5.1. 1 Table 3.5.1.2 Table 3.5.1.3 Table 3.5.1.4 Table 3.5.2 Table 3 5.3 Table 3.5.4 Table 3 5.5.1 Table 3.5.5.2 Table 3 5.6.1 Table 3.5.6.2 Table 3 5.6.3 !"able 3.5.7.1 !"able 3.5.7.2 !"able 3.5.8.1 !"able 3 5.8 2 !"able 3.5.8.3 Table l 5.9.1 Table 3 59 2 rablc35.10.1 rablt: 3.5.1 0.2 rable 3.5.1 0.3 Tabk 3.6.1 Table 3.6.1.1 rablc 3.6.1.2 rable 3 6.1.3 rable 3 6 2 I fable 3 6.2.2 Table 3.6.2.3 Table 3 6.3.1 Table 3 6 3.2 Table 3 ~.2.1 Out come of the night peak load flow of the constructed transmission sub network. Out come of the day peak load flow of the transmission sub network. Out come of the night peak load flow of the sub network as it has been operated. Out come of the day peak load flow for the sub network as it is being operated. Recorded peak loads in the months of July and August 2005 Network configuration of A ltcrnative 0 I Network configuration of Alternative 02 Network configuration of Alternative 03 Network configuration of Alternative 04 Network configuration of Altemative 05 Network configuration of Alternative 06 Network configuration of Alternatrve 07 Network configuration of Alternative 08 Network configuration of Altemati\C 09 Network configuration of Alternatr,·e 10 Rated load:. of the conductors Demanded and delivered peak power m month of February 2005 Demanded and delivered peak power in month of March 2005 Demanded and delivered peak power in month of May 2005.f Demanded and delivered peak power in month of July 200) Demanded and de livered peak power in month of August 2005 Day and night voltages at the peak in the months of July and August 2005 at the adjacent buses Outcome ot the load flow for Alternative 0 I in night peak Outcome ofthe load flow for Alternative 01 in night peak when the "Asia Power" PSis failed to deliver power. Outcome of the load flow for Alternative 0 I in night peak with Kelaniya GS Outcome ofthe load flow for Alternative 01 in day peak with Kelaniya GS Outcome of the load flow for Alternative 02 in night peak Outcome of the load flow for Alternative 03 in night peak Outcome of the load flo\\ for Alternative 04 in night peak Outcome olthe load flow for Alternative 05 in night peak Outcome of the load flow for Alternative 05 in da) peak Outcome of the load flow for Alternauve 06 in night peak Outcome of the load flow for Alternative 06 in day peak Voltages of adJacent buses at day and nrght peaks fo~ Alternative 06 Outcome of the load flow for Alternative 07 m night peak Outcome of the load flow for Alternative 07 in day peak Outcome of the load flow for Alternative 08 in night peak Outcome ot the load flow for Altemative 08 in~ peaJ..: Voltages of adjacent buse~ at da} and night peak'!. for Alternati'e 08 Outcome of the load OO\\ for Alternative 09 in night peak Outcome of the load Oo'' for Alternative 09 in day peak Outcome of the load Oow for Alternative 10 in night peak Outcome of the load flow for Alternative I 0 in day peak . ..-' Voltages of adjacent buses at day and night peaks for Alternative l 0 Summar) of percentage of line loads Outcome ot the load flo,, lor Alterna'live 11 in night peak Outcome of the load flow for A lternatrve I 1 in day peak . • Vo ltages of adjacent bust:s at day and night peaks for Alternativt: t'r· Outcome of the load flow for Alternatr\t! 12 in night peaJ..: " Outcome of the load flow for A lternatl\ c 12 in day peak Voltages of adJacent buses Jt dJy and night peaks for Alternative 12 Percentage of ma,unum line loads in each configuration Total system net\\ ork loss with each sub network configuration Comparison of construction costs \'II 7 7 10 10 13 14 14 IS 15 IS IS 16 16 16 17 17 19 19 19 20 :w 20 21 21 2·1 24 27 27 30 30 33 33 33 37 ~~ - ' 39 :9 :9 ·13 '' ~ ·' 4] 46 46 49 49 50 50 ~~ 53 53 56 56 57 5Cl List of Principal Svmbols ACSR All Conductor Steel Reinforced AP Asia Power Biya Biyagama Capa Capacity Cct Circuit CEB Ceylon Electricity Board Cond. Conductor Condi. Condition Con. Constructed cc degree Centigrade 0 /C Double Circuit GS Grid Substation Gen. Generated IPP Independent Power Producer Kela Kelaniya Kolo Kolonnawa Kotu Kotugoda N Number of circuits Ope. Operating PS Power Station PSS/E Power System Simulator for Engineering S/C Single Circuit Sapu Sapugaskanda .. ~ " \'Ill j .... v ... .. ~ ,,